The overcurrent relays for the line protection and loads connected at the buses are shown in the figure.

The relays are $IDMT$ in nature having the characteristic

$t_{op}=\dfrac{0.14\times \text{Time Multiplier Setting}}{(\text{Plug Setting Multiplier})^{0.02}-1}$

The maximum and minimum fault currents at bus $B$ are $2000$ $A$ and $500$ $A$ respectively. Assuming the time multiplier setting and plug setting for relay $R_B$ to be $0.1$ and $5A$ respectively, the operating time of $R_B$ (in seconds) is ______________

Please log in or register to answer this question.

Related questions

0 0 votes
0 0 answers
57
57 views
gatecse asked Feb 23
57 views
The operating characteristic of a reactance relay is given by $X \leq 1 \Omega$, where $X$ is the reactance calculated by the relay. Its operating characteristic in the a...
0 0 votes
0 0 answers
394
394 views
Misbah Ghaya asked Feb 11, 2017
394 views
For a $400$ $km$ long transmission line, the series impedance is ($0.0$ + $j0.5$) $Ω/km$ and the shunt admittance is ($0.0$ + $j5.0$) $μmho$/$km$. The magnitude of the se...
0 0 votes
0 0 answers
533
533 views
Misbah Ghaya asked Jan 29, 2017
533 views
In the balanced $3$-phase, $50$ Hz, circuit shown below, the value of inductance $(L)$ is $10$ mH. The value of the capacitance $(C)$ for which all the line currents are ...
0 0 votes
0 0 answers
296
296 views
Misbah Ghaya asked Feb 11, 2017
296 views
The figure shows one period of the output voltage of an inverter.$\alpha$ should be chosen such that $60^{\circ}<\alpha <90^{\circ}$. If $rms$ value of the fundamental c...
Position: